To manage your application login from here to get to the Dashboard
How to Apply for Load Change/Division?
[Existing consumer may need to increase/decrease the electricity load as well as new meter connection. To change load, please follow the instructions below.]
Step 1: Login to the OCSMS web portal with ‘Username’ and ‘Password’.
Step 2: Click on the link “New Connection/Load Change” menu from the left panel of the dashboard. A new application form will appear with three tabs.
Step 3: Go to Basic Information page, provide basic information and click on “Save & Continue” button.
Step 4: Go to Connection/Meter List page, click on “Add New Meter” button, provide necessary information of connection and click on “Save & Continue” button.
Step 5: Go to Attachment page, attach necessary documents as required and click on “Save” button.
Step 6: To submit application, click on “Submit & Close” button. A confirmation popup will appear with Yes/No option.
Step 7: Click on “Yes” option. Application will be submitted successfully and user will get a confirmation SMS.